Ready on 100%

16.06.2015

Five top-priority houses of the settlement "Dutch quarter" are ready on 100%. On seven more houses facade works are being held. The site improvement is in full spate – kerb stone is being set up in pedestrian boulevards, the stone blocks pavement is being put on sidewalks; geo web is being put on parking spaces. On houses of the second turn in-situ concreting are finished. Installation of the enclosure structures is coming to the end. In houses № 13-21 internal block works, parapets setting, installation of air shafts are finished, and also all roofing works are performed. In the same houses teams on laying of water supply system, the sewerage, electricity supply system got to work. Readiness on these works is from 35% to 70%.